The contract

Contract sum
₦12,006,498,448 Official record
Contractor
LEVANT CONSTRUCTION LIMITED
Awarded by
STATE TENDERS BOARD
Reference
DSPPC/CNO/1700
Awarded on
July 23, 2025
Due date
June 23, 2026
Contract period
12 MONTHS
Reported progress
65%
Past its date by
63 days
Category
Works
Coordinates
5.77111, 6.09970

What it is meant to be

The project involves the rehabilitation and asphalt overlay of the Ekpan/Oviore/Ovu/Okpara Inland/Isiokolo/Kokori Road to restore it to a durable and motorable condition. The work includes repairing damaged sections, resurfacing the road, and installing or improving drainage systems to prevent water damage and prolong the lifespan of the pavement. The project is expected to significantly improve transportation across the affected communities, reduce travel time, and enhance safety for road users. It will also facilitate the movement of goods and services, thereby promoting economic growth and development in the area. Additionally, the rehabilitation work will create employment opportunities and contribute to sustainable infrastructural development in Ethiope East Local Government Area. -->

What has been checked

Not yet checked No citizen report or inspection is recorded yet.

The ground at these coordinates

Satellite view of the site on 2025-01-11
Before the award 2025-01-11 · 0.0% of the site under cloud
Satellite view of the site on 2026-03-12
Since the award 2026-03-12 · 2.9% of the site under cloud

Two clear looks at the coordinate the register publishes, 2.56 km across. Ten metres to a pixel. This shows whether the ground at a published coordinate changed between two dates. It does not show what was built, who built it, or whether it works, and it is not field evidence. From satellite

Copernicus Sentinel-2, rendered by the archive. A picture of the ground is not a site visit: it cannot say what was built, who built it, or whether it works.

Awarding body State Tenders Board awarded this contract. Delta State has around 30 boards, agencies and commissions that spend public money outside the ministry structure, each with a head of its own. The names of these office holders are not yet published.

Sources for this record

What we knowValueClassSource
contract_sum 12006498448.38 Official record Delta State Public Procurement Commission · original
project_progress 65 Official record Delta State Public Procurement Commission · original
project_status Ongoing Official record Delta State Public Procurement Commission · original
contract_awarded_on 2025-07-23 Official record Delta State Public Procurement Commission · original
expected_completion 2026-06-23 Official record Delta State Public Procurement Commission · original
project_field_evidence not yet published Not yet published OpenDelta
satellite_clear_looks 2 From satellite Copernicus Sentinel-2 via Earth Search (Element 84) · original

What people who have been there say

Reports from people who have visited, alongside the register's progress figure.

No reports on this project yet

No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published

How we know this

Responses to this record

Published as received, in the sender's words, without editing for length.

No response has been received. Everything on this page is drawn from what institutions published; if it is wrong, or incomplete, the reply is published here unedited beside it.

Respond to this record How the right of reply works