Ethiope East › Project
Supply and distribution of pupils furniture to public primary schools in delta central senatorial district.
The contract
- Contract sum
- ₦267,552,377 Official record
- Contractor
- SETAL CONS. ENTERPRISES
- Awarded by
- MINISTRY OF PRIMARY EDUCATION
- Reference
- DSPPC/CNO/2044
- Awarded on
- March 4, 2026
- Due date
- May 20, 2026
- Contract period
- 12 WEEKS
- Reported progress
- 0%
- Past its date by
- 97 days
- Category
- Goods
- Coordinates
- 5.67825, 5.96211
What it is meant to be
The project involves the supply and distribution of pupils’ furniture to public primary schools across the Delta Central Senatorial District. The initiative is designed to provide adequate desks and chairs for pupils, thereby improving classroom conditions and ensuring that students have comfortable seating during lessons. By providing appropriate furniture for pupils, the project helps create a more conducive learning environment in public primary schools. This intervention is expected to enhance pupils’ concentration during classes, support effective teaching, and contribute to improved educational outcomes across the district. -->
What has been checked
The ground at these coordinates
The satellite could not see this site. 17 scenes offered, 10 checked, the site clouded over in every one. Cloud hid this site, so a satellite comparison is not possible. From satellite
Copernicus Sentinel-2, rendered by the archive. A picture of the ground is not a site visit: it cannot say what was built, who built it, or whether it works.
Sources for this record
| What we know | Value | Class | Source |
|---|---|---|---|
| contract_sum | 267552376.65 | Official record | Delta State Public Procurement Commission · original |
| project_progress | 0 | Official record | Delta State Public Procurement Commission · original |
| project_status | New Projects | Official record | Delta State Public Procurement Commission · original |
| contract_awarded_on | 2026-03-04 | Official record | Delta State Public Procurement Commission · original |
| expected_completion | 2026-05-20 | Official record | Delta State Public Procurement Commission · original |
| project_field_evidence | not yet published | Not yet published | OpenDelta |
| satellite_clear_looks | 1 | From satellite | Copernicus Sentinel-2 via Earth Search (Element 84) · original |
What people who have been there say
Reports from people who have visited, alongside the register's progress figure.
No reports on this project yet
No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published
Responses to this record
Published as received, in the sender's words, without editing for length.
No response has been received. Everything on this page is drawn from what institutions published; if it is wrong, or incomplete, the reply is published here unedited beside it.