Construction of 464m discharge drain on aladja ogbe-ijoh road to evacuate flood on bezi road aladja in udu local government area.
The contract
- Contract sum
- ₦235,646,988 Official record
- Contractor
- RCT NIGERIA LIMITED
- Awarded by
- MINISTRY OF WORKS (HIGHWAYS & URBAN ROADS)
- Reference
- DSPPC/CNO/1723
- Awarded on
- Aug. 8, 2025
- Due date
- Jan. 30, 2026
- Contract period
- 6 MONTHS
- Reported progress
- 100%
- Category
- Works
- Coordinates
- 5.48686, 5.75632
What it is meant to be
The Construction of 464m Discharge Drain on Aladja–Ogbe-Ijoh Road to evacuate flood on Bezi Road in Aladja, by the Governor of Delta State, His Excellency Rt. Hon. Sheriff Oborevwori, in this and beyond, is aimed at addressing persistent flooding challenges and improving stormwater management in the area. The project involves 464m length of drains. The scope of works for the drain consist of site clearance, construction of concrete drains and slabs. This intervention is expected to reduce flooding, improve road durability, and enhance the safety and accessibility of the affected communities. It also contributes to environmental sustainability and supports resilient infrastructural development within the local government area and beyond. -->
What has been checked
Sources for this record
| What we know | Value | Class | Source |
|---|---|---|---|
| contract_sum | 235646987.5 | Official record | Delta State Public Procurement Commission · original |
| project_progress | 100 | Official record | Delta State Public Procurement Commission · original |
| project_status | Completed | Official record | Delta State Public Procurement Commission · original |
| contract_awarded_on | 2025-08-08 | Official record | Delta State Public Procurement Commission · original |
| expected_completion | 2026-01-30 | Official record | Delta State Public Procurement Commission · original |
| project_field_evidence | not yet published | Not yet published | OpenDelta |
What people who have been there say
Reports from people who have visited, alongside the register's progress figure.
No reports on this project yet
No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published
Responses to this record
Published as received, in the sender's words, without editing for length.
No response has been received. Everything on this page is drawn from what institutions published; if it is wrong, or incomplete, the reply is published here unedited beside it.
Respond to this record How the right of reply works