Udu › Project
Renovation of high court otor-udu and high court obiaruku
The contract
- Contract sum
- ₦284,173,345 Official record
- Contractor
- UKPECHEKE ENTERPRISES
- Awarded by
- MINISTRY OF HOUSING
- Reference
- DSPPC/CNO/2183
- Awarded on
- July 7, 2026
- Due date
- Jan. 28, 2027
- Contract period
- 7 MONTHS
- Reported progress
- 0%
- Category
- Works
- Coordinates
- 5.83867, 6.15800
What it is meant to be
The renovation of the High Courts at Otor-Udu and Obiaruku in Delta State, by Rt. Hon. Sheriff Oborevwori, is aimed at upgrading judicial infrastructure through the rehabilitation and modernization of court facilities to provide a safe, functional, and conducive environment for the administration of justice. The scope of work includes two courses of block walls, re-roofing of the entire building and fixing of the ceiling, electrical wiring and fittings, plumbing works, tiling of the floor, steel stanchions and tank, replacement of doors and vandalized windows and protectors, fencing, gate house and re-painting the entire complex. The project will improve the condition of the court buildings, enhance the welfare of judicial officers, court staff, and court users, preserve public assets, and strengthen efficient justice delivery in Delta State. -->
What has been checked
Sources for this record
| What we know | Value | Class | Source |
|---|---|---|---|
| contract_sum | 284173344.72 | Official record | Delta State Public Procurement Commission · original |
| project_progress | 0 | Official record | Delta State Public Procurement Commission · original |
| project_status | New Projects | Official record | Delta State Public Procurement Commission · original |
| contract_awarded_on | 2026-07-07 | Official record | Delta State Public Procurement Commission · original |
| expected_completion | 2027-01-28 | Official record | Delta State Public Procurement Commission · original |
| project_field_evidence | not yet published | Not yet published | OpenDelta |
What people who have been there say
Reports from people who have visited, alongside the register's progress figure.
No reports on this project yet
No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published
Responses to this record
Published as received, in the sender's words, without editing for length.
No response has been received. Everything on this page is drawn from what institutions published; if it is wrong, or incomplete, the reply is published here unedited beside it.
Respond to this record How the right of reply works