Ndokwa East › Project
Construction of ogbedigbo-afor road, with a spur to obi palace road, ndokwa east local government area
The contract
- Contract sum
- ₦1,831,430,652 Official record
- Contractor
- GOBAS CONSTRUCTION LIMITED
- Awarded by
- STATE TENDERS BOARD
- Reference
- DSPPC/CNO/2158
- Awarded on
- June 10, 2026
- Due date
- May 10, 2027
- Contract period
- 12 MONTHS
- Reported progress
- 10%
- Category
- Works
- Coordinates
- 5.78050, 6.45621
What it is meant to be
The construction of the Ogbedigbo–Afor Road, with a spur to Obi Palace Road, in Ndokwa East Local Government Area, by Rt. Hon. Sheriff Oborevwori. The length of the road is 1,430m, 130m spur to the Obi Palace, 12.5m clearance width and 7.3m pavement width. The scope of work for the project includes scarification of failed asphaltic pavement, earthworks involving removal of unsuitable materials and subsequent fill using both river sharp sand and lateritic earth-fill materials, concrete works comprising drains, culverts and access slabs as pavement works involving crushed stone base course followed by two layers hot rolled asphalt (HRA). Upon completion, the project will provide a durable road network that facilitates the efficient movement of residents, traders, farmers, and visitors, improves access to the Obi Palace, markets, schools, healthcare facilities, and other essential public services as well as contributes to sustainable infrastructure development and improved living standards in Ndokwa East Local Government Area. -->
What has been checked
Sources for this record
| What we know | Value | Class | Source |
|---|---|---|---|
| contract_sum | 1831430652.17 | Official record | Delta State Public Procurement Commission · original |
| project_progress | 10 | Official record | Delta State Public Procurement Commission · original |
| project_status | Ongoing | Official record | Delta State Public Procurement Commission · original |
| contract_awarded_on | 2026-06-10 | Official record | Delta State Public Procurement Commission · original |
| expected_completion | 2027-05-10 | Official record | Delta State Public Procurement Commission · original |
| project_field_evidence | not yet published | Not yet published | OpenDelta |
What people who have been there say
Reports from people who have visited, alongside the register's progress figure.
No reports on this project yet
No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published
Responses to this record
Published as received, in the sender's words, without editing for length.
No response has been received. Everything on this page is drawn from what institutions published; if it is wrong, or incomplete, the reply is published here unedited beside it.
Respond to this record How the right of reply works