Isoko South › Project
Additional work on the reconstruction and rehabilitation of the failed uzere/asaba-ase culverts and the rehabilitation of the failed section along uzere/asaba-ase road, isoko south and ndokwa east local government area
The contract
- Contract sum
- ₦3,165,862,580 Official record
- Contractor
- LEBTECH CONSTRUCTION LIMITED
- Awarded by
- STATE TENDERS BOARD
- Reference
- DSPPC/CNO/1681
- Awarded on
- July 10, 2025
- Due date
- June 10, 2026
- Contract period
- 12 MONTHS
- Reported progress
- 55%
- Past its date by
- 76 days
- Category
- Works
- Coordinates
- 5.30032, 6.29752
What it is meant to be
The project involves additional works on the reconstruction and rehabilitation of failed culverts along the Uzere/Asaba-Ase road, as well as the repair of damaged sections of the road with additional 20m span reinforced concrete bridge. These interventions are aimed at restoring the structural integrity of the road and ensuring proper drainage to prevent further deterioration. This development will improve road safety, enhance connectivity, and facilitate the movement of people and goods between communities in Isoko South Local Government Area and Ndokwa East Local Government Area. It will also support economic activities and contribute to sustainable infrastructure development in the region. -->
What has been checked
The ground at these coordinates
One of these looks is disputed and we are not calling it a comparison. The archive's own classifier reports the site clear; the picture is full of near-white pixels anyway. That is either low cloud the classifier missed or bare ground, and nothing here can tell you which — which is exactly why a picture from orbit is not a site visit. From satellite
Copernicus Sentinel-2, rendered by the archive. A picture of the ground is not a site visit: it cannot say what was built, who built it, or whether it works.
Sources for this record
| What we know | Value | Class | Source |
|---|---|---|---|
| contract_sum | 3165862579.99 | Official record | Delta State Public Procurement Commission · original |
| project_progress | 55 | Official record | Delta State Public Procurement Commission · original |
| project_status | Ongoing | Official record | Delta State Public Procurement Commission · original |
| contract_awarded_on | 2025-07-10 | Official record | Delta State Public Procurement Commission · original |
| expected_completion | 2026-06-10 | Official record | Delta State Public Procurement Commission · original |
| project_field_evidence | not yet published | Not yet published | OpenDelta |
| satellite_clear_looks | 0 | From satellite | Copernicus Sentinel-2 via Earth Search (Element 84) · original |
What people who have been there say
Reports from people who have visited, alongside the register's progress figure.
No reports on this project yet
No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published
Responses to this record
Published as received, in the sender's words, without editing for length.
No response has been received. Everything on this page is drawn from what institutions published; if it is wrong, or incomplete, the reply is published here unedited beside it.
Respond to this record How the right of reply works