OpenDeltaDelta State

Isoko South › Project

Rehabilitation/improvement of water supply scheme at umeh town, isoko south local government area

Isoko South · Umeh Town, Isoko South Local Government Area

Budget
Award
Build
Verified

The contract

Contract sum
₦139,305,290 Official record
Contractor
ELOFABIO VENTURES
Awarded by
SMALL TOWNS WATER SUPPLY AND SANITATION AGENCY
Reference
DSPPC/CNO/1298/97
Awarded on
Sept. 11, 2025
Due date
Dec. 4, 2025
Contract period
12 WEEKS
Reported progress
100%
Category
Works
Coordinates
5.26880, 6.15204

What it is meant to be

The rehabilitation and improvement of the water supply scheme at Umeh Town, Isoko South Local Government Area is aimed at improving the availability and reliability of potable water for residents. The project will restore and enhance the water supply system, improve access to safe and clean water, support better hygiene and sanitation practices, reduce dependence on unsafe water sources, improve public health, and contribute to sustainable water infrastructure and improved living conditions in Umeh Town. -->

What has been checked

Not yet checked No citizen report or inspection is recorded yet.
Awarding body Small Towns Water Supply And Sanitation Agency awarded this contract. Delta State has around 30 boards, agencies and commissions that spend public money outside the ministry structure, each with a head of its own. The names of these office holders are not yet published.

Sources for this record

What we knowValueClassSource
contract_sum 139305290.05 Official record Delta State Public Procurement Commission · original
project_progress 100 Official record Delta State Public Procurement Commission · original
project_status Completed Official record Delta State Public Procurement Commission · original
contract_awarded_on 2025-09-11 Official record Delta State Public Procurement Commission · original
expected_completion 2025-12-04 Official record Delta State Public Procurement Commission · original
project_field_evidence not yet published Not yet published OpenDelta

What people who have been there say

Reports from people who have visited, alongside the register's progress figure.

No reports on this project yet

No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published

How we know this

Responses to this record

Published as received, in the sender's words, without editing for length.