Ukwuani › Project
Infrastructural interventions at esumu-uku primary school obiaruku and igwete primary school, amai ukwuani local government area
The contract
- Contract sum
- ₦119,841,596 Official record
- Contractor
- MAMATEE WATER SOLUTIONS ENTERPRISES
- Awarded by
- MINISTRY OF PRIMARY EDUCATION
- Reference
- DSPPC/CNO/1536
- Awarded on
- Oct. 22, 2025
- Due date
- Jan. 1, 2026
- Contract period
- 12 WEEKS
- Reported progress
- 100%
- Category
- Works
- Coordinates
- 5.75295, 6.20442
What it is meant to be
The infrastructural intervention project at Esumu-Uku Primary School in Obiaruku and Igwete Primary School in Amai, located within Ukwuani Local Government Area of Delta State, was designed to improve the quality, safety, and inclusiveness of the learning environment for pupils and teachers. Many public primary schools in rural communities face challenges such as dilapidated classrooms, inadequate furniture, poor sanitation facilities, and limited access to safe water, all of which hinder effective teaching and learning. This project addressed these gaps through the rehabilitation and/or construction of classroom blocks, provision of desks and chairs, and improvement of essential facilities such as toilets and water points, thereby creating conducive spaces that support child-friendly education. By strengthening basic educational infrastructure, the intervention contributes to increased school enrolment, attendance, and retention, particularly among girls and vulnerable children, while enhancing the overall wellbeing of the school community. The project supports national and global commitments to equitable access to quality basic education and aligns with Sustainable Development Go
What has been checked
Sources for this record
| What we know | Value | Class | Source |
|---|---|---|---|
| contract_sum | 119841596.47 | Official record | Delta State Public Procurement Commission · original |
| project_progress | 100 | Official record | Delta State Public Procurement Commission · original |
| project_status | Completed | Official record | Delta State Public Procurement Commission · original |
| contract_awarded_on | 2025-10-22 | Official record | Delta State Public Procurement Commission · original |
| expected_completion | 2026-01-01 | Official record | Delta State Public Procurement Commission · original |
| project_field_evidence | not yet published | Not yet published | OpenDelta |
What people who have been there say
Reports from people who have visited, alongside the register's progress figure.
No reports on this project yet
No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published
Responses to this record
Published as received, in the sender's words, without editing for length.
No response has been received. Everything on this page is drawn from what institutions published; if it is wrong, or incomplete, the reply is published here unedited beside it.
Respond to this record How the right of reply works