Oshimili South › Project
Renovation of the pointer newspaper office asaba, oshimili south local government area.
The contract
- Contract sum
- ₦43,139,230 Official record
- Contractor
- VENO TOUCH ENERGY LIMITED
- Awarded by
- MINISTRY OF HIGHER EDUCATION
- Reference
- DSPPC/CNO/1912
- Awarded on
- Jan. 7, 2026
- Due date
- May 7, 2026
- Contract period
- 20 WEEKS
- Reported progress
- 65%
- Past its date by
- 110 days
- Category
- Works
- Coordinates
- 6.20509, 6.72037
What it is meant to be
The renovation of The Pointer Newspaper Office in Asaba, located in Oshimili South Local Government Area of Delta State, was undertaken to restore and upgrade the physical condition of the state-owned media facility to support efficient information dissemination and administrative operations. Over time, the office infrastructure had deteriorated due to wear, aging, and environmental exposure, affecting staff productivity, safety, and the quality of media production processes. The project therefore focused on rehabilitating the building structure, refurbishing workspaces, improving electrical and mechanical installations, and upgrading essential office facilities to create a safe, functional, and modern working environment. Through these improvements, the intervention enhances the operational capacity of The Pointer as a public information platform, supporting timely news production, editorial activities, and communication services to the public. The project contributes to improved working conditions for media professionals and strengthens the institutional role of the newspaper in promoting public awareness, transparency, and civic engagement across Delta State. Overall, the renova
What has been checked
Sources for this record
| What we know | Value | Class | Source |
|---|---|---|---|
| contract_sum | 43139229.54 | Official record | Delta State Public Procurement Commission · original |
| project_progress | 65 | Official record | Delta State Public Procurement Commission · original |
| project_status | Ongoing | Official record | Delta State Public Procurement Commission · original |
| contract_awarded_on | 2026-01-07 | Official record | Delta State Public Procurement Commission · original |
| expected_completion | 2026-05-07 | Official record | Delta State Public Procurement Commission · original |
| project_field_evidence | not yet published | Not yet published | OpenDelta |
What people who have been there say
Reports from people who have visited, alongside the register's progress figure.
No reports on this project yet
No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published
Responses to this record
Published as received, in the sender's words, without editing for length.
No response has been received. Everything on this page is drawn from what institutions published; if it is wrong, or incomplete, the reply is published here unedited beside it.
Respond to this record How the right of reply works