Replacement of burnt 1 (no) 300kva.33/0.400kv transformer at the drug revolving fund office asaba, oshimili south local government area

Oshimili South · Drug Revolving Fund Office, Asaba

Budget
Award
Build
Verified

The contract

Contract sum
₦35,658,027 Official record
Contractor
PRESNOL GLOBAL ENTERPRISE
Awarded by
MINISTRY OF ENERGY
Reference
DSPPC/CNO/1872.
Awarded on
Dec. 2, 2025
Due date
Feb. 17, 2026
Contract period
12 WEEKS
Reported progress
100%
Category
Goods
Coordinates
6.20593, 6.69589

What it is meant to be

The replacement of the burnt 300KVA, 33/0.400KV transformer at the Drug Revolving Fund Office, Asaba, Oshimili South Local Government Area, by Rt. Hon. Sheriff Oborevwori, is aimed at restoring a reliable electricity supply to the facility and improving its electrical infrastructure. The project will ensure stable power for the operation of essential office and pharmaceutical activities, reduce disruptions caused by inadequate power supply, improve operational efficiency, protect electrical equipment, and support effective healthcare-related services and pharmaceutical supply operations in Delta State. -->

What has been checked

Not yet checked No citizen report or inspection is recorded yet.
Awarding body Ministry Of Energy awarded this contract. A ministry's accounting officer is its permanent secretary. Delta State has 29 of them. The names of these office holders are not yet published.

Sources for this record

What we knowValueClassSource
contract_sum 35658026.81 Official record Delta State Public Procurement Commission · original
project_progress 100 Official record Delta State Public Procurement Commission · original
project_status Completed Official record Delta State Public Procurement Commission · original
contract_awarded_on 2025-12-02 Official record Delta State Public Procurement Commission · original
expected_completion 2026-02-17 Official record Delta State Public Procurement Commission · original
project_field_evidence not yet published Not yet published OpenDelta

What people who have been there say

Reports from people who have visited, alongside the register's progress figure.

No reports on this project yet

No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published

How we know this

Responses to this record

Published as received, in the sender's words, without editing for length.

No response has been received. Everything on this page is drawn from what institutions published; if it is wrong, or incomplete, the reply is published here unedited beside it.

Respond to this record How the right of reply works

Also here