Demolition of 1no. 6 classroom block/construction of 1no. 5 classroom block at eke-anya primary school okogbele, oshimili south local government area
The contract
- Contract sum
- ₦99,725,676 Official record
- Contractor
- COLLINSOBI INTEGRATED SERVICES LTD
- Awarded by
- MINISTRY OF PRIMARY EDUCATION
- Reference
- DSPPC/CNO/1634
- Awarded on
- May 12, 2025
- Due date
- July 28, 2025
- Contract period
- 12 WEEKS
- Reported progress
- 100%
- Category
- Works
- Coordinates
- 6.08304, 6.69967
What it is meant to be
The demolition of the existing 1-No. six-classroom block and construction of a new 1-No. five-classroom block at Eke-Anya Primary School, Okogbele, Oshimili South Local Government Area, by Rt. Hon. Sheriff Oborevwori, is aimed at replacing the existing classroom facility with a safer and more functional learning environment. The project will provide improved classroom accommodation, enhance the safety and comfort of pupils and teachers, support effective teaching and learning, improve the quality of basic education infrastructure, and contribute to better educational outcomes and sustainable community development in Oshimili South Local Government Area. -->
What has been checked
Sources for this record
| What we know | Value | Class | Source |
|---|---|---|---|
| contract_sum | 99725675.6 | Official record | Delta State Public Procurement Commission · original |
| project_progress | 100 | Official record | Delta State Public Procurement Commission · original |
| project_status | Completed | Official record | Delta State Public Procurement Commission · original |
| contract_awarded_on | 2025-05-12 | Official record | Delta State Public Procurement Commission · original |
| expected_completion | 2025-07-28 | Official record | Delta State Public Procurement Commission · original |
| project_field_evidence | not yet published | Not yet published | OpenDelta |
What people who have been there say
Reports from people who have visited, alongside the register's progress figure.
No reports on this project yet
No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published
Responses to this record
Published as received, in the sender's words, without editing for length.
No response has been received. Everything on this page is drawn from what institutions published; if it is wrong, or incomplete, the reply is published here unedited beside it.
Respond to this record How the right of reply works