OpenDeltaDelta State

Oshimili North › Project

Rehabilitation/reconstruction of 4.5km section of asaba/ugbolu road (phase ii), oshimili north local government area

Oshimili North · Asaba-Ugbolu Road

Budget
Award
Build
Verified

The contract

Contract sum
₦3,946,519,965 Official record
Contractor
SINOMA INVESTMENT INTERNATIONAL LTD
Awarded by
STATE TENDERS BOARD
Reference
DSPPC/CNO/1608
Awarded on
April 28, 2025
Due date
March 28, 2026
Contract period
12 MONTHS
Reported progress
100%
Category
Works
Coordinates
6.30898, 6.68787

What it is meant to be

The rehabilitation and reconstruction of the 4.5km section of Asaba/Ugbolu Road (Phase II) in Oshimili North Local Government Area, by Rt. Hon. Sheriff Oborevwori, is aimed at improving road infrastructure and connectivity between Asaba and Ugbolu. The scope of work for the project includes clearing of site, scarification of failed bituminous surface, removal of topsoil and unsuitable materials, earth fill, crushed stone base, regulation of potholes and pavement surfacing consisting of binder course on the section for reconstruction/shoulders and wearing course on the entire carriageway of the 4.5km length road. The project will improve the condition and durability of the road, facilitate the movement of people and agricultural produce, reduce travel time and transportation costs, improve access to markets and essential services, enhance road safety, support economic activities, and contribute to sustainable development in Oshimili North Local Government Area. -->

What has been checked

Not yet checked No citizen report or inspection is recorded yet.
Awarding body State Tenders Board awarded this contract. Delta State has around 30 boards, agencies and commissions that spend public money outside the ministry structure, each with a head of its own. The names of these office holders are not yet published.

Sources for this record

What we knowValueClassSource
contract_sum 3946519964.69 Official record Delta State Public Procurement Commission · original
project_progress 100 Official record Delta State Public Procurement Commission · original
project_status Completed Official record Delta State Public Procurement Commission · original
contract_awarded_on 2025-04-28 Official record Delta State Public Procurement Commission · original
expected_completion 2026-03-28 Official record Delta State Public Procurement Commission · original
project_field_evidence not yet published Not yet published OpenDelta

What people who have been there say

Reports from people who have visited, alongside the register's progress figure.

No reports on this project yet

No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published

How we know this

Responses to this record

Published as received, in the sender's words, without editing for length.

No response has been received. Everything on this page is drawn from what institutions published; if it is wrong, or incomplete, the reply is published here unedited beside it.

Respond to this record How the right of reply works

Also here