Okpe › Project
Development of external work at some facilities at southern delta university, orerokpe campus
The contract
- Contract sum
- ₦698,000,000 Official record
- Contractor
- BRINTS ENGINEERING SERVICES LIMITED
- Awarded by
- MINISTRY OF HIGHER EDUCATION
- Reference
- DSPPC/CNO/1833
- Awarded on
- Nov. 21, 2025
- Due date
- May 21, 2026
- Contract period
- 6 MONTHS
- Reported progress
- 45%
- Past its date by
- 96 days
- Category
- Works
- Coordinates
- 5.55807, 6.22376
What it is meant to be
The project titled Development of External Works at Some Facilities at Southern Delta University, Orerokpe Campus involves the execution of approved civil and environmental works aimed at improving the functionality, accessibility, and aesthetic quality of the university environment. The project is designed to support the effective use of existing facilities by providing well-planned external infrastructure in line with the development objectives of Southern Delta University and the Delta State Government. The scope of works includes site clearing, earthworks, landscaping, paving, drainage construction, walkways, kerbs, and other associated external works as detailed in the approved drawings and contract documents. All construction activities are being carried out in accordance with relevant engineering standards, environmental regulations, and safety requirements prescribed by the Delta State Ministry. Upon completion, the project is expected to enhance environmental orderliness, improve pedestrian and vehicular movement, and contribute to a conducive academic and institutional environment at the Orerokpe Campus. -->
What has been checked
The ground at these coordinates
Two clear looks at the coordinate the register publishes, 2.56 km across. Ten metres to a pixel. This shows whether the ground at a published coordinate changed between two dates. It does not show what was built, who built it, or whether it works, and it is not field evidence. From satellite
Copernicus Sentinel-2, rendered by the archive. A picture of the ground is not a site visit: it cannot say what was built, who built it, or whether it works.
Sources for this record
| What we know | Value | Class | Source |
|---|---|---|---|
| contract_sum | 698000000.0 | Official record | Delta State Public Procurement Commission · original |
| project_progress | 45 | Official record | Delta State Public Procurement Commission · original |
| project_status | Ongoing | Official record | Delta State Public Procurement Commission · original |
| contract_awarded_on | 2025-11-21 | Official record | Delta State Public Procurement Commission · original |
| expected_completion | 2026-05-21 | Official record | Delta State Public Procurement Commission · original |
| project_field_evidence | not yet published | Not yet published | OpenDelta |
| satellite_clear_looks | 2 | From satellite | Copernicus Sentinel-2 via Earth Search (Element 84) · original |
What people who have been there say
Reports from people who have visited, alongside the register's progress figure.
No reports on this project yet
No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published
Responses to this record
Published as received, in the sender's words, without editing for length.
No response has been received. Everything on this page is drawn from what institutions published; if it is wrong, or incomplete, the reply is published here unedited beside it.
Respond to this record How the right of reply works