Aniocha North › Project
Infrastructural upgrade at nkwor primary school, idumuje-unor aniocha north local government area
The contract
- Contract sum
- ₦119,983,607 Official record
- Contractor
- PALISADE CONTRACTING
- Awarded by
- MINISTRY OF PRIMARY EDUCATION
- Reference
- DSPPC/CNO/1950
- Awarded on
- Feb. 6, 2026
- Due date
- May 21, 2026
- Contract period
- 12 WEEKS
- Reported progress
- 65%
- Past its date by
- 96 days
- Category
- Works
- Coordinates
- 6.13601, 6.17074
What it is meant to be
This project aims to assess and implement infrastructural upgrades at Nkwor Primary School, Idumuje-Unor, in Aniocha North Local Government Area. The focus is on evaluating existing facilities and identifying areas that require improvement, including classrooms, teaching aids, sanitation, and recreational spaces. The study intends to provide recommendations for infrastructural interventions that will create a more conducive learning environment for students, enhance teaching efficiency, and support academic achievement. Additionally, the project explores the relationship between improved infrastructure and student learning outcomes. By examining how upgraded facilities can influence classroom engagement, teaching quality, and overall school performance, the study seeks to provide actionable insights for policymakers, education authorities, and community stakeholders. The findings are expected to contribute to sustainable educational development in the region and align with global efforts to achieve quality education for all. -->
What has been checked
The ground at these coordinates
Two clear looks at the coordinate the register publishes, 2.56 km across. Ten metres to a pixel. This shows whether the ground at a published coordinate changed between two dates. It does not show what was built, who built it, or whether it works, and it is not field evidence. From satellite
Copernicus Sentinel-2, rendered by the archive. A picture of the ground is not a site visit: it cannot say what was built, who built it, or whether it works.
Sources for this record
| What we know | Value | Class | Source |
|---|---|---|---|
| contract_sum | 119983607.19 | Official record | Delta State Public Procurement Commission · original |
| project_progress | 65 | Official record | Delta State Public Procurement Commission · original |
| project_status | Ongoing | Official record | Delta State Public Procurement Commission · original |
| contract_awarded_on | 2026-02-06 | Official record | Delta State Public Procurement Commission · original |
| expected_completion | 2026-05-21 | Official record | Delta State Public Procurement Commission · original |
| project_field_evidence | not yet published | Not yet published | OpenDelta |
| satellite_clear_looks | 2 | From satellite | Copernicus Sentinel-2 via Earth Search (Element 84) · original |
What people who have been there say
Reports from people who have visited, alongside the register's progress figure.
No reports on this project yet
No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published
Responses to this record
Published as received, in the sender's words, without editing for length.
No response has been received. Everything on this page is drawn from what institutions published; if it is wrong, or incomplete, the reply is published here unedited beside it.
Respond to this record How the right of reply works