Uvwie › Project
Construction of ejirue/ovhokwo street, ekpan in uvwie local government area
The contract
- Contract sum
- ₦249,985,217 Official record
- Contractor
- CROMWELL TECHNOLOGIES LIMITED
- Awarded by
- WARRI/UVWIE AND ENVIRONS SPECIAL AREA DEVELOPMENT AGENCY
- Reference
- DSPPC/CNO/2049
- Awarded on
- March 11, 2026
- Due date
- Aug. 11, 2026
- Contract period
- 6 MONTHS
- Reported progress
- 5%
- Past its date by
- 14 days
- Category
- Works
- Coordinates
- 5.56387, 5.72981
What it is meant to be
The construction of Ejirue/Ovhokwo Street in Ekpan, Uvwie Local Government Area, is a vital infrastructure project aimed at improving the road network and overall accessibility within the community. The project includes site clearing, grading, installation of effective drainage systems, and the application of durable road surfacing materials to ensure long-term usability. This development is expected to address issues such as poor road conditions, erosion, and seasonal flooding, thereby enhancing safety and ease of movement for residents and road users. Moreover, the project is expected to stimulate socio-economic growth by improving access to residential and commercial areas, thereby encouraging increased economic activities. Better road infrastructure will attract investments, enhance property values, and improve the standard of living for the people in the area. Additionally, the construction phase will create employment opportunities for both skilled and unskilled workers, contributing to local income generation. Overall, the project promotes sustainable urban development by fostering a more connected, accessible, and resilient community. -->
What has been checked
The ground at these coordinates
Two clear looks at the coordinate the register publishes, 2.56 km across. Ten metres to a pixel. This shows whether the ground at a published coordinate changed between two dates. It does not show what was built, who built it, or whether it works, and it is not field evidence. From satellite
Copernicus Sentinel-2, rendered by the archive. A picture of the ground is not a site visit: it cannot say what was built, who built it, or whether it works.
Sources for this record
| What we know | Value | Class | Source |
|---|---|---|---|
| contract_sum | 249985216.56 | Official record | Delta State Public Procurement Commission · original |
| project_progress | 5 | Official record | Delta State Public Procurement Commission · original |
| project_status | Ongoing | Official record | Delta State Public Procurement Commission · original |
| contract_awarded_on | 2026-03-11 | Official record | Delta State Public Procurement Commission · original |
| expected_completion | 2026-08-11 | Official record | Delta State Public Procurement Commission · original |
| project_field_evidence | not yet published | Not yet published | OpenDelta |
| satellite_clear_looks | 2 | From satellite | Copernicus Sentinel-2 via Earth Search (Element 84) · original |
What people who have been there say
Reports from people who have visited, alongside the register's progress figure.
No reports on this project yet
No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published
Responses to this record
Published as received, in the sender's words, without editing for length.
No response has been received. Everything on this page is drawn from what institutions published; if it is wrong, or incomplete, the reply is published here unedited beside it.
Respond to this record How the right of reply works