Reconstruction of general hospital road in oghara, ethiope west local government area
The contract
- Contract sum
- ₦1,048,390,428 Official record
- Contractor
- MURP HENDRIKS INTERNATIONAL LIMITED
- Awarded by
- STATE TENDERS BOARD
- Reference
- DSPPC/CNO/1375/95
- Awarded on
- Sept. 16, 2024
- Due date
- March 3, 2025
- Contract period
- 6 MONTHS
- Reported progress
- 100%
- Category
- Works
- Coordinates
- 5.93847, 5.67953
What it is meant to be
The reconstruction of General Hospital Road in Oghara is aimed at improving access to the healthcare facility and surrounding areas by upgrading the existing road infrastructure. The project involves 1.060m of road length, including earthworks comprising site clearance, scarification, removal of unsuitable materials, river sharp sand fill and laying of crushed stone base course, concrete works comprising of drains, single box culverts, pavement surfacing consisting of two layers of Hot Rolled Asphat (HRA) and thermoplasting road marking. The project is expected to facilitate easier and quicker access to medical services, thereby improving healthcare delivery in the area. It will also reduce travel time, enhance safety for road users, and support economic activities within the community. Additionally, the reconstruction work will create employment opportunities and contribute to sustainable infrastructural development in Ethiope West Local Government Area. -->
What has been checked
Sources for this record
| What we know | Value | Class | Source |
|---|---|---|---|
| contract_sum | 1048390428.25 | Official record | Delta State Public Procurement Commission · original |
| project_progress | 100 | Official record | Delta State Public Procurement Commission · original |
| project_status | Completed | Official record | Delta State Public Procurement Commission · original |
| contract_awarded_on | 2024-09-16 | Official record | Delta State Public Procurement Commission · original |
| expected_completion | 2025-03-03 | Official record | Delta State Public Procurement Commission · original |
| project_field_evidence | not yet published | Not yet published | OpenDelta |
What people who have been there say
Reports from people who have visited, alongside the register's progress figure.
No reports on this project yet
No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published
Responses to this record
Published as received, in the sender's words, without editing for length.
No response has been received. Everything on this page is drawn from what institutions published; if it is wrong, or incomplete, the reply is published here unedited beside it.