Okpe › Project
Construction of mereje/erogho road (phase i), okpe local government area
The contract
- Contract sum
- ₦13,771,787,574 Official record
- Contractor
- ROADWELL CONTRACTING LIMITED
- Awarded by
- STATE TENDERS BOARD
- Reference
- DSPPC/CNO/1710
- Awarded on
- Aug. 5, 2025
- Due date
- Jan. 29, 2027
- Contract period
- 18 MONTHS
- Reported progress
- 40%
- Category
- Works
- Coordinates
- 5.43413, 5.94758
What it is meant to be
The construction of Mereje/Erogho Road (Phase I) is aimed at developing a durable and motorable road network to improve access between communities in Okpe Local Government Area. The project includes 12.77km length of road includes site clearing, scarification of failed stone base sections, removal of topsoil and unsuitable materials, sharp sand fill, crushed stone base, demolition of undersized and non-functional drainage structure, construction of reinforced concrete drains, access slabs, box/ring culverts at flood prone sections and pavement surfacing consisting of two layers of hot rolled asphalt, binder and wearing courses on the carriageway as well as pavement markings. The project is expected to enhance transportation, reduce travel time, and improve safety for road users. It will also support economic activities by facilitating the movement of goods and services, thereby boosting local trade and development. Additionally, the construction work will create employment opportunities and contribute to sustainable infrastructural growth in the area. -->
What has been checked
The ground at these coordinates
Two clear looks at the coordinate the register publishes, 2.56 km across. Ten metres to a pixel. This shows whether the ground at a published coordinate changed between two dates. It does not show what was built, who built it, or whether it works, and it is not field evidence. From satellite
Copernicus Sentinel-2, rendered by the archive. A picture of the ground is not a site visit: it cannot say what was built, who built it, or whether it works.
Sources for this record
| What we know | Value | Class | Source |
|---|---|---|---|
| contract_sum | 13771787574.41 | Official record | Delta State Public Procurement Commission · original |
| project_progress | 40 | Official record | Delta State Public Procurement Commission · original |
| project_status | Ongoing | Official record | Delta State Public Procurement Commission · original |
| contract_awarded_on | 2025-08-05 | Official record | Delta State Public Procurement Commission · original |
| expected_completion | 2027-01-29 | Official record | Delta State Public Procurement Commission · original |
| project_field_evidence | not yet published | Not yet published | OpenDelta |
| satellite_clear_looks | 2 | From satellite | Copernicus Sentinel-2 via Earth Search (Element 84) · original |
What people who have been there say
Reports from people who have visited, alongside the register's progress figure.
No reports on this project yet
No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published
Responses to this record
Published as received, in the sender's words, without editing for length.
No response has been received. Everything on this page is drawn from what institutions published; if it is wrong, or incomplete, the reply is published here unedited beside it.
Respond to this record How the right of reply works