OpenDeltaDelta State

Uvwie › Project

Reconstruction of a dual carriage way on the warri/sapele/benin road from the end of the u-turn at the spare parts market, effurun to after ohore junction before omenta bridge, uvwie and okpe local government area.

OkpeUvwie · Warri/Sapele/Benin Road

Budget
Award
Build
Verified

The contract

Contract sum
₦35,754,101,487 Official record
Contractor
CCECC
Awarded by
STATE TENDERS BOARD
Reference
DSPPC/CNO/1727
Awarded on
Aug. 14, 2025
Due date
July 14, 2026
Contract period
12 MONTHS
Reported progress
65%
Past its date by
42 days
Category
Works
Coordinates
5.55575, 5.78437

What it is meant to be

The reconstruction of a 5,000m dual carriageway on the Warri/Sapele/Benin Road, from the end of the U-Turn at the Spare Parts Market, Effurun to after Ohore Junction before Omenta Bridge, under the administration of Rt. Hon. Sheriff Oborevwori, is aimed at upgrading a major transportation corridor in the state. The project involves expanding the existing road into a dual carriageway, rehabilitating failed sections, constructing drainage systems, and improving road alignment to ensure durability and smooth traffic flow. This intervention will significantly reduce traffic congestion, enhance road safety, and improve connectivity between key commercial and residential areas in Uvwie Local Government Area and Okpe Local Government Area. It will also facilitate the movement of goods and services, promote economic activities, and contribute to the overall socio-economic development of the region. -->

What has been checked

Not yet checked No citizen report or inspection is recorded yet.

The ground at these coordinates

Satellite view of the site on 2026-02-15
Since the award 2026-02-15 · unclear

One of these looks is disputed and we are not calling it a comparison. The archive's own classifier reports the site clear; the picture is full of near-white pixels anyway. That is either low cloud the classifier missed or bare ground, and nothing here can tell you which — which is exactly why a picture from orbit is not a site visit. From satellite

Copernicus Sentinel-2, rendered by the archive. A picture of the ground is not a site visit: it cannot say what was built, who built it, or whether it works.

Awarding body State Tenders Board awarded this contract. Delta State has around 30 boards, agencies and commissions that spend public money outside the ministry structure, each with a head of its own. The names of these office holders are not yet published.

Sources for this record

What we knowValueClassSource
contract_sum 35754101487.29 Official record Delta State Public Procurement Commission · original
project_progress 65 Official record Delta State Public Procurement Commission · original
project_status Ongoing Official record Delta State Public Procurement Commission · original
contract_awarded_on 2025-08-14 Official record Delta State Public Procurement Commission · original
expected_completion 2026-07-14 Official record Delta State Public Procurement Commission · original
project_field_evidence not yet published Not yet published OpenDelta
satellite_clear_looks 0 From satellite Copernicus Sentinel-2 via Earth Search (Element 84) · original

What people who have been there say

Reports from people who have visited, alongside the register's progress figure.

No reports on this project yet

No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published

How we know this

Responses to this record

Published as received, in the sender's words, without editing for length.

No response has been received. Everything on this page is drawn from what institutions published; if it is wrong, or incomplete, the reply is published here unedited beside it.

Respond to this record How the right of reply works