Warri South › Project

Rehabilitation and asphalt overlay of edukugho street, off iyara road in warri south local government area

Warri South · Edukugho Street, off Iyara Road

Budget
Award
Build
Verified

The contract

Contract sum
₦349,938,944 Official record
Contractor
ORUESE INTERNATIONAL NIGERIA ENTERPRISES
Awarded by
WARRI/UVWIE AND ENVIRONS SPECIAL AREA DEVELOPMENT AGENCY
Reference
DSPPC/CNO/1673
Awarded on
July 11, 2025
Due date
Dec. 24, 2025
Contract period
6 MONTHS
Reported progress
100%
Category
Works
Coordinates
5.50869, 5.76407

What it is meant to be

The rehabilitation and asphalt overlay of Edukugho Street, off Iyara Road in Warri South Local Government Area, under the administration of Rt. Hon. Sheriff Oborevwori, is aimed at restoring the road to a durable and motorable condition. The 490m length of road with 7.3m pavement width, 980m length of drain and 170m failed asphalt sections, begins at Iyara road and terminates at Atse-Olu road. The scope of work for the 490m length of road includes earthworks comprising the removal of unsuitable materials, filling with sharp sand, and laying a stone base; and concrete works comprising concrete drains and slabs. It also involves asphalt works of one layer of Hot Roll Asphalt wearing course. This intervention will enhance accessibility and improve road safety for residents and commuters. It will also facilitate the movement of goods and services and contribute to the overall socio-economic well-being of the residents. -->

What has been checked

Not yet checked No citizen report or inspection is recorded yet.
Awarding body Warri/Uvwie And Environs Special Area Development Agency awarded this contract. Delta State has around 30 boards, agencies and commissions that spend public money outside the ministry structure, each with a head of its own. The names of these office holders are not yet published.

Sources for this record

What we knowValueClassSource
contract_sum 349938943.93 Official record Delta State Public Procurement Commission · original
project_progress 100 Official record Delta State Public Procurement Commission · original
project_status Completed Official record Delta State Public Procurement Commission · original
contract_awarded_on 2025-07-11 Official record Delta State Public Procurement Commission · original
expected_completion 2025-12-24 Official record Delta State Public Procurement Commission · original
project_field_evidence not yet published Not yet published OpenDelta

What people who have been there say

Reports from people who have visited, alongside the register's progress figure.

No reports on this project yet

No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published

How we know this

Responses to this record

Published as received, in the sender's words, without editing for length.

No response has been received. Everything on this page is drawn from what institutions published; if it is wrong, or incomplete, the reply is published here unedited beside it.

Respond to this record How the right of reply works

Also here