Uvwie › Project
Widening of nnpc housing complex road from edjeba junction to the brigde and asphalt overlay of ekpan link road from first bank to refinery road ekpan in uvwie local government area
The contract
- Contract sum
- ₦749,891,568 Official record
- Contractor
- LEVANT CONSTRUCTION LIMITED
- Awarded by
- STATE TENDERS BOARD
- Reference
- DSPPC/CNO/1678
- Awarded on
- July 17, 2025
- Due date
- Jan. 30, 2026
- Contract period
- 6 MONTHS
- Reported progress
- 100%
- Category
- Works
- Coordinates
- 5.56919, 5.74760
What it is meant to be
The rehabilitation and asphalt overlay of Etuwewe Road in Warri South Local Government Area, under the administration of Rt. Hon. Sheriff Oborevwori, is aimed at restoring the road to a durable and motorable condition. The 1,755m length of road consists of 755m of the section to be widened from Edjeba junction to the foot of the bridge and 1,000m length of asphalt overlay of dual carriageway on Ekpan link road from First Bank to refinery road. The widening of the road, with a width of 2.75m on either side, is necessary considering the height of the existing road and as a major route for motorists traversing to other parts of Effurun and Warri Metropolis. The scope of works involves earthworks, including removal of unsuitable materials, filling with sharp sand material and laying of a stone base and one layer of Asphalt of 40mm thickness wearing course. It also consists of concrete works comprising concrete drainage and slabs. This intervention will enhance accessibility and improve road safety for residents and commuters. It will also facilitate the movement of goods and services, support local businesses, and contribute to the area's overall socio-economic development. -->
What has been checked
Sources for this record
| What we know | Value | Class | Source |
|---|---|---|---|
| contract_sum | 749891567.93 | Official record | Delta State Public Procurement Commission · original |
| project_progress | 100 | Official record | Delta State Public Procurement Commission · original |
| project_status | Completed | Official record | Delta State Public Procurement Commission · original |
| contract_awarded_on | 2025-07-17 | Official record | Delta State Public Procurement Commission · original |
| expected_completion | 2026-01-30 | Official record | Delta State Public Procurement Commission · original |
| project_field_evidence | not yet published | Not yet published | OpenDelta |
What people who have been there say
Reports from people who have visited, alongside the register's progress figure.
No reports on this project yet
No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published
Responses to this record
Published as received, in the sender's words, without editing for length.
No response has been received. Everything on this page is drawn from what institutions published; if it is wrong, or incomplete, the reply is published here unedited beside it.
Respond to this record How the right of reply works