Okpe › Project
Construction of four bed male student hostel (lot 2a) at southern delta university, orerokpe campus
The contract
- Contract sum
- ₦688,512,677 Official record
- Contractor
- EBRENT PRIME GLOBAL CONTRACT
- Awarded by
- MINISTRY OF HIGHER EDUCATION
- Reference
- DSPPC/CNO/2102
- Awarded on
- April 29, 2026
- Due date
- March 29, 2027
- Contract period
- 12 MONTHS
- Reported progress
- 0%
- Category
- Works
- Coordinates
- 5.55291, 6.23734
What it is meant to be
The construction of a four-bed male student hostel (Lot 2A) at Southern Delta University, Orerokpe Campus, under the administration of Rt. Hon. Sheriff Oborevwori, is aimed at providing adequate and comfortable accommodation for students within the university environment. The scope of work comprises the construction of a male hostel building with rooms to accommodate four beds per room with ensuite bath/toilet, common room, tuck shop, general kitchen, general laundry and porter's lodge. This intervention will help reduce accommodation challenges faced by students, provide a conducive learning environment, and improve students’ comfort and security on campus. It will also enhance the infrastructural development of the institution, promote better academic performance, and contribute to the overall growth and attractiveness of the university in Orerokpe. -->
What has been checked
Sources for this record
| What we know | Value | Class | Source |
|---|---|---|---|
| contract_sum | 688512676.78 | Official record | Delta State Public Procurement Commission · original |
| project_progress | 0 | Official record | Delta State Public Procurement Commission · original |
| project_status | New Projects | Official record | Delta State Public Procurement Commission · original |
| contract_awarded_on | 2026-04-29 | Official record | Delta State Public Procurement Commission · original |
| expected_completion | 2027-03-29 | Official record | Delta State Public Procurement Commission · original |
| project_field_evidence | not yet published | Not yet published | OpenDelta |
What people who have been there say
Reports from people who have visited, alongside the register's progress figure.
No reports on this project yet
No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published
Responses to this record
Published as received, in the sender's words, without editing for length.
No response has been received. Everything on this page is drawn from what institutions published; if it is wrong, or incomplete, the reply is published here unedited beside it.
Respond to this record How the right of reply works