Construction of perimeter block wall fence with gate house at oha secondary school, oha, okpe local government area.

Okpe · Oha Secondary School, Oha,

Budget
Award
Build
Verified

The contract

Contract sum
₦147,392,563 Official record
Contractor
IFUDE ASINI VENTURES
Awarded by
MINISTRY OF SECONDARY EDUCATION
Reference
DSPPC/CNO/2120
Awarded on
May 14, 2026
Due date
Aug. 6, 2026
Contract period
12 WEEKS
Reported progress
0%
Past its date by
19 days
Category
Works
Coordinates
5.62957, 5.85912

What it is meant to be

The construction of a perimeter block wall fence with a gate house at Oha Secondary School in Okpe Local Government Area, by His Excellency, Rt. Hon. Sheriff Oborevwori, is aimed at improving security and protecting school facilities, students, and staff within the institution. The project involves the construction of a perimeter block wall fence, gate house, entrance gates, and related structural works to ensure controlled access and proper demarcation of the school premises. The project will enhance safety within the school environment, prevent encroachment and vandalism, and create a more secure and conducive atmosphere for teaching and learning activities. It will also contribute to improved educational infrastructure, better school management, and socio-economic development within the community. -->

What has been checked

Not yet checked No citizen report or inspection is recorded yet.

The ground at these coordinates

The satellite could not see this site. 7 scenes offered, 7 checked, the site clouded over in every one. Cloud hid this site, so a satellite comparison is not possible. From satellite

Copernicus Sentinel-2, rendered by the archive. A picture of the ground is not a site visit: it cannot say what was built, who built it, or whether it works.

Awarding body Ministry Of Secondary Education awarded this contract. A ministry's accounting officer is its permanent secretary. Delta State has 29 of them. The names of these office holders are not yet published.

Sources for this record

What we knowValueClassSource
contract_sum 147392563.28 Official record Delta State Public Procurement Commission · original
project_progress 0 Official record Delta State Public Procurement Commission · original
project_status New Projects Official record Delta State Public Procurement Commission · original
contract_awarded_on 2026-05-14 Official record Delta State Public Procurement Commission · original
expected_completion 2026-08-06 Official record Delta State Public Procurement Commission · original
project_field_evidence not yet published Not yet published OpenDelta
satellite_clear_looks 1 From satellite Copernicus Sentinel-2 via Earth Search (Element 84) · original

What people who have been there say

Reports from people who have visited, alongside the register's progress figure.

No reports on this project yet

No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published

How we know this

Responses to this record

Published as received, in the sender's words, without editing for length.

No response has been received. Everything on this page is drawn from what institutions published; if it is wrong, or incomplete, the reply is published here unedited beside it.

Respond to this record How the right of reply works

Also here