Isoko North › Project
Construction of 33kv overhead (oh) high voltage (hv) line from emevor through otor-owhe to isoko round about and rehabilitation of vandalized portions of the existing 33kv line between iyede and ellu in isoko north local government area.
The contract
- Contract sum
- ₦310,000,000 Official record
- Contractor
- BERRY TOUCH NIG. ENTERPRISE
- Awarded by
- MINISTRY OF ENERGY
- Reference
- DSPPC/CNO/2187
- Awarded on
- July 10, 2026
- Due date
- Oct. 2, 2026
- Contract period
- 12 WEEKS
- Reported progress
- 0%
- Category
- Works
- Coordinates
- 5.43941, 6.10465
What it is meant to be
The construction of a 33KV overhead (OH) high-voltage (HV) line from Emevor through Otor-Owhe to Isoko Roundabout and the rehabilitation of vandalized portions of the existing 33KV line between Iyede and Ellu in Isoko North Local Government Area, by Rt. Hon. Sheriff Oborevwori, is aimed at expanding and restoring electricity transmission infrastructure to ensure reliable power distribution across the affected communities. The project will improve the stability and efficiency of electricity supply, reduce power outages, support residential, commercial, and industrial activities, enhance socio-economic development, and contribute to sustainable energy infrastructure in Isoko North Local Government Area. -->
What has been checked
Sources for this record
| What we know | Value | Class | Source |
|---|---|---|---|
| contract_sum | 310000000.0 | Official record | Delta State Public Procurement Commission · original |
| project_progress | 0 | Official record | Delta State Public Procurement Commission · original |
| project_status | New Projects | Official record | Delta State Public Procurement Commission · original |
| contract_awarded_on | 2026-07-10 | Official record | Delta State Public Procurement Commission · original |
| expected_completion | 2026-10-02 | Official record | Delta State Public Procurement Commission · original |
| project_field_evidence | not yet published | Not yet published | OpenDelta |
What people who have been there say
Reports from people who have visited, alongside the register's progress figure.
No reports on this project yet
No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published
Responses to this record
Published as received, in the sender's words, without editing for length.
No response has been received. Everything on this page is drawn from what institutions published; if it is wrong, or incomplete, the reply is published here unedited beside it.
Respond to this record How the right of reply works