Ndokwa West › Project
Reconstruction of access road into kwale free trade zone, first entrance gate, ndokwa west local government area.
The contract
- Contract sum
- ₦6,003,040,123 Official record
- Contractor
- BRYHILVAN INTEGRATED
- Awarded by
- STATE TENDERS BOARD
- Reference
- DSPPC/CNO/2173
- Awarded on
- June 22, 2026
- Due date
- May 22, 2027
- Contract period
- 12 MONTHS
- Reported progress
- 0%
- Category
- Works
- Coordinates
- 5.71085, 6.44131
What it is meant to be
The reconstruction of the access road to the Kwale Free Trade Zone First Entrance Gate in Ndokwa West Local Government Area, by Rt. Hon. Sheriff Oborevwori, is aimed at improving access to the Free Trade Zone by providing a durable and efficient road network that supports industrial and commercial activities. The total length of road include 5,640m, clearance width 15m, pavement width 7.3m, width of hard shoulder (2 sides) 3m and length of kerbs (roundabout) 200m. The scope of the work includes site clearance, removal of topsoil and unstable materials, placement of lateritic fill, crushed stone base, concrete works (walkways, kerbs), pavement surfacing with hot rolled asphalt (HRA) binder and wearing courses and thermoplastic road marking. -->
What has been checked
Sources for this record
| What we know | Value | Class | Source |
|---|---|---|---|
| contract_sum | 6003040122.75 | Official record | Delta State Public Procurement Commission · original |
| project_progress | 0 | Official record | Delta State Public Procurement Commission · original |
| project_status | New Projects | Official record | Delta State Public Procurement Commission · original |
| contract_awarded_on | 2026-06-22 | Official record | Delta State Public Procurement Commission · original |
| expected_completion | 2027-05-22 | Official record | Delta State Public Procurement Commission · original |
| project_field_evidence | not yet published | Not yet published | OpenDelta |
What people who have been there say
Reports from people who have visited, alongside the register's progress figure.
No reports on this project yet
No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published
Responses to this record
Published as received, in the sender's words, without editing for length.
No response has been received. Everything on this page is drawn from what institutions published; if it is wrong, or incomplete, the reply is published here unedited beside it.
Respond to this record How the right of reply works