Warri South › Project
Construction of benikrukru township roads (phase ii), warri south-west local government area
The contract
- Contract sum
- ₦3,277,952,618 Official record
- Contractor
- VICTONJO INTERNATIONAL NIGERIA LIMITED
- Awarded by
- STATE TENDERS BOARD
- Reference
- DSPPC/CNO/1597
- Awarded on
- Sept. 2, 2025
- Due date
- Aug. 2, 2026
- Contract period
- 12 MONTHS
- Reported progress
- 75%
- Past its date by
- 23 days
- Category
- Works
- Coordinates
- 5.64250, 5.28470
What it is meant to be
The construction of the Benikrukru Township Roads (Phase II) in Warri South-West Local Government Area, by Rt. Hon. Sheriff Oborevwori, is aimed at expanding and improving the township road network to enhance accessibility and socio-economic development within the community. The scope of works for the 2,885m length of road includes site clearing, scarification of failed interlocking stones, removal of unsuitable materials, sharp river sand filling and stone base; concrete works comprising of 200mm thick concrete drains, access slabs, culverts; pavement surfacing comprising of 200mm thick concrete pavement, fixing of steel reinforcement, construction of expansion joints and sealing with bitumen. The project will provide durable road infrastructure that facilitates the safe and efficient movement of residents, traders, and visitors, improves access to schools, healthcare facilities, markets, and other public amenities, reduces transportation costs, stimulates local commerce and investment and contributes to sustainable infrastructure development and improved quality of life in Warri South-West Local Government Area. -->
What has been checked
The ground at these coordinates
Two clear looks at the coordinate the register publishes, 2.56 km across. Ten metres to a pixel. This shows whether the ground at a published coordinate changed between two dates. It does not show what was built, who built it, or whether it works, and it is not field evidence. From satellite
Copernicus Sentinel-2, rendered by the archive. A picture of the ground is not a site visit: it cannot say what was built, who built it, or whether it works.
Sources for this record
| What we know | Value | Class | Source |
|---|---|---|---|
| contract_sum | 3277952617.9 | Official record | Delta State Public Procurement Commission · original |
| project_progress | 75 | Official record | Delta State Public Procurement Commission · original |
| project_status | Ongoing | Official record | Delta State Public Procurement Commission · original |
| contract_awarded_on | 2025-09-02 | Official record | Delta State Public Procurement Commission · original |
| expected_completion | 2026-08-02 | Official record | Delta State Public Procurement Commission · original |
| project_field_evidence | not yet published | Not yet published | OpenDelta |
| satellite_clear_looks | 2 | From satellite | Copernicus Sentinel-2 via Earth Search (Element 84) · original |
What people who have been there say
Reports from people who have visited, alongside the register's progress figure.
No reports on this project yet
No independent check is recorded yet. If you have passed this site and a figure here looks wrong, you can tell us. Not yet published
Responses to this record
Published as received, in the sender's words, without editing for length.
No response has been received. Everything on this page is drawn from what institutions published; if it is wrong, or incomplete, the reply is published here unedited beside it.
Respond to this record How the right of reply works